Due to continued evaluations regarding line pack availability and the duration of the Arrowhead Tie-in maintenance scheduled for Saturday, December 8, 2007, North Baja Pipeline has determined that the ability to make deliveries during the scheduled maintenance can be increased. Therefore, throughput at the Ogilby delivery point will be increased from 120 to 150 MMcf/d for gas day Saturday, December 8th.
Should you have any questions, please call a Gas Transportation Scheduler at 503.833.4300, option 1.