The North Baja Pipeline Shutdown Schedule has been updated. Please refer below for the most current information or click here to go directly to the maintenance schedule.
Arrowhead Tie-in
The Arrowhead Tie-in work previously scheduled for Monday, December 3, 2007, has been moved to Saturday, December 8, 2007. Due to limited line pack availability the previously posted capacity at Ogilby has been reduced from 180 to 120 MMcf/d.
Ehrenberg Meter Tie-in
The Ehrenberg Meter Tie-in work previously scheduled for Thursday, December 6, 2007, has been moved to Tuesday, December 11, 2007. The maintenance is anticipated to take up to 8 days to complete. The impacted throughput capability at Ehrenberg will remain restricted to 240 MMcf/d.
If you have any questions, please call a Gas Transportation Coordinator at 503.833.4300, Option 1.